Today in the Systems Engineering and Integration(SEaI) division, students and mentors tested the gyroscope assembly (PN: 1010167) and integrated the part into our system. SEaI also began developing software routines for a closed loop control of the robot when…
Today, the team worked to optimize the kicker and arm. The surgical tubing on the kicker was replaced with trampoline springs, to make it more easy to get a repeatable and known force. A gas spring was installed on the first stage of the arm to aid in arm…
Today, the design team worked to design the polycarbonate side shields for the robots. Due to weight issues, we will probably not be able to implement all of the polycarbonate shields on the robot. The team also designed the cutouts which will be made on the…
Today, the design team completed the design on replacements for the Hard Stop Mounting Plates. The replacements will extend the plate back to support the PTO shaft directly above the gearboxes after said shaft was identified as a potential point of failure.…
Today the kicker plate was shortened. The shorter plate contacts the ball higher up on the ball, giving it a flatter trajectory. A rope was added as a hard stop, which prevents the kicker from contacting the roller system. Original video unavailable. Original…
The Robot Was Crated Tonight. Final Weights of Shipped Components: Drivebase (without cRio) - 52 lbs Arm - 19 lbs The superstructure was withheld as part of the 65 lb withholding allowance.
Today, we (almost) finished assembling the drivetrain and kicker winch gearboxes. We also made further progress on the bumper fabrication. Here's some photos to pass your time.
Today progress was made on the bumper pieces, including machining the wood and corner brackets. We hope to finish the bumper structure by the end of Friday, to begin material cutting and sewing on Saturday. At this time, I do not expect the bumpers to be…
MANUFACTURING The manufacturing team worked hard today to machine the ratchets and finish the bar grabbing clamps. The lathe was also hard at work making spacers, standoffs and shafts. ASSEMBLY After the arms returned from the powder coat shop today, several…